SCHEDULE

Calendar Icon

Construction is anticipated to begin in summer 2021 and last approximately two years concluding in summer 2023.

To minimize impacts and maintain traffic movement for local and regional travelers, construction will be completed in two stages. Below is the tentative construction plan.

A paper flip calendar

Stage 1

Installation of temporary trestle over San Joaquin River
Construction of west side of new bridge

Stage 2

Demolition of old bridge
Removal of tempory trestle over San Joaquin River
Roadway Work
Bridge Opening
Clock icon

Work Hours

Work will typically occur 7 a.m. to 5 p.m. Monday-Friday as well as occasionally on Saturday and Sunday. Night work may also occur on Carpenter Road and during certain construction activities requiring 24-hour work such as drilling foundation piers.

What to Expect During Construction

Traffic delays, detours and typical construction-related noise and dust.

  • Temporary closure of Carpenter Road may occur on occasion from 10 p.m. to 6 a.m., Monday – Friday with a detour to Ruble Road.
  • Lane restrictions may also occur to allow for construction of approach embankments on each side of the San Joaquin River with one-way traffic control and onsite flaggers.

Detour information will be made available prior to closure.

Access for local property owners will be maintained throughout construction and road closure near properties will be coordinated on an individual basis.

Public safety access will be maintained at all times.

flagger icon

Please observe all traffic control signs and instructions of onsite workers. We apologize for any inconvenience this bridge replacement project may cause and appreciate your patience